Coomler Contracting Inc.
Coomler Contracting Inc.
Jan 25, 2023
1/5
West Lafayette apartment complex is making some great progress! The elevator shafts are up. Building pad 1 is being poured with all pipe work completed. Building pad 2 has all pipework complete and waiting to get poured. All sanitary pipe work is now complete and we are moving on to the water.